PROJECTS // STOKE CITY COUNCIL

Sutherland Primary

DESIGN & BUILD

PROJECTS // STOKE CITY COUNCIL

Sutherland Primary

DESIGN & BUILD

SECTOR
VALUE
DURATION
EDUCATION
£2.5M
6 MONTHS

Objective

As part of an ongoing Framework Agreement, we were appointed by the City of Stoke-on-Trent Council to provide a temporary classroom solution on the playing field of Sutherland Primary Academy, whilst the main school buildings were demolished and a new facility built. We had to overcome the presence on site of a large badger colony, which resulted in a scheme redesign and the imposition of restricted working practises during the construction phase.

Solution

With enabling works commencing end of the July and a non-negotiable requirement for the school to be fully functional by the end of the October half term, the project was delivered on time and we continued to provide an on-site maintenance service until the Academy moved into its permanent facility.

KEY TASKS

  • The construction of an engineered ground foundation solution to provide a load-bearing platform
  • Temporary storm and foul water drainage solution including the construction of a foul water pumping station and storm water balancing pond
  • Provision of a temporary mains power solution ahead of the construction of a new substation and uprated incoming permanent mains
  • Supply, installation, fit out and ongoing hire of modular-build temporary classroom units, configured to provide teaching spaces for Reception through to Year 6, a library, practical rooms and a dedicated Dining/Canteen facility
  • Provision of access roads, ramps, hard and soft play areas
sutherland-slider-3
sutherland-slider-0
sutherland-slider-1
sutherland-slider-2
sutherland-slider-5
previous arrow
next arrow
sutherland-slider-3
sutherland-slider-0
sutherland-slider-1
sutherland-slider-2
sutherland-slider-5
previous arrow
next arrow